Once a maintenance plan is established, the owner/operator implements it. The maintenance cycle starts with the pre-outage planning, continues through the outage, and ends with the post-outage assessment. As one would expect most gas turbine components have a finite life or expected life in the turbine under the GE performance guidelines. During the maintenance or outage cycle, owners and operators decide to use the component “as is,” repair the component, or replace the component. This post-outage assessment provides the basis for planning the next outage.

Throughout this outage process, the owner/ operator will be faced with many difficult decisions that will determine unit reliability, maintenance costs, and operating benefit.

CONTENTS:

K.J. Pallos GE E Abstract . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1

Operation and Maintenance Considerations. . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1

Repair vs. Replacement . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1

Component Repairs. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3

Nozzles. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .3

Stage One Nozzle . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3

Activated Diffusion Healing: Distortion-Free Nozzle Restoration . . . . . . . . . . . .5

Nozzle Modifications . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6

Stages Two and Three Nozzle Repair . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6

Advanced Bucket Repair . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .  7

Rotors . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10

Combustion Hardware . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .12

Combustor . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .12

Transition Pieces . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13

Fuel Nozzles . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14

Component Enhancement . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .  15

Extendor™ . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .15

Coatings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .15

Compressor Corrosion Protection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .15

Turbine Corrosion/Oxidation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15

Thermal Barrier Coatings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16

Service Background . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .18

Summary. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .  20

Appendix — Destructive Analysis: A Tool for Understanding Component Lif. 21

GE Meeting Industry’s Demands . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21

Material Issues. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21

Limitations of Non-Destructive Evaluation . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21

The Need for Destructive Analysis . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .21

Benefits of Destructive Analysis . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .22

Customer Satisfaction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23

Find Out More . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .23

List of Figures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24

List of Tables . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .25

LINK DOWNLOAD


EBOOK - CÔNG NGHỆ SỬA CHỮA TURBINE KHÍ (30 trang)

Once a maintenance plan is established, the owner/operator implements it. The maintenance cycle starts with the pre-outage planning, continues through the outage, and ends with the post-outage assessment. As one would expect most gas turbine components have a finite life or expected life in the turbine under the GE performance guidelines. During the maintenance or outage cycle, owners and operators decide to use the component “as is,” repair the component, or replace the component. This post-outage assessment provides the basis for planning the next outage.

Throughout this outage process, the owner/ operator will be faced with many difficult decisions that will determine unit reliability, maintenance costs, and operating benefit.

CONTENTS:

K.J. Pallos GE E Abstract . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1

Operation and Maintenance Considerations. . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1

Repair vs. Replacement . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1

Component Repairs. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3

Nozzles. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .3

Stage One Nozzle . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3

Activated Diffusion Healing: Distortion-Free Nozzle Restoration . . . . . . . . . . . .5

Nozzle Modifications . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6

Stages Two and Three Nozzle Repair . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6

Advanced Bucket Repair . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .  7

Rotors . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10

Combustion Hardware . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .12

Combustor . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .12

Transition Pieces . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13

Fuel Nozzles . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14

Component Enhancement . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .  15

Extendor™ . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .15

Coatings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .15

Compressor Corrosion Protection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .15

Turbine Corrosion/Oxidation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15

Thermal Barrier Coatings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16

Service Background . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .18

Summary. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .  20

Appendix — Destructive Analysis: A Tool for Understanding Component Lif. 21

GE Meeting Industry’s Demands . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21

Material Issues. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21

Limitations of Non-Destructive Evaluation . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21

The Need for Destructive Analysis . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .21

Benefits of Destructive Analysis . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .22

Customer Satisfaction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23

Find Out More . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .23

List of Figures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24

List of Tables . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .25